Hospitals run hot water and steam systems around the clock, so scale causes real problems there. Mercy Hospital in Council Bluffs, Iowa, installed an MHD unit and tracked the results for three years.

The investment

The MHD unit cost $6,400 and installation added $310, for a total investment of $6,710.

The savings

Annual steam cost savings ($5,600 × 3 years)$16,800
Annual labour & chemical savings ($9,694 × 3 years)$29,082
Equipment savings$28,000
Total 3-year savings$63,882

That is roughly 9.5 times the original investment, and the steam, labour and chemical savings alone paid for the unit within the first year.

What other facilities can learn

The largest single saving was not energy. It was labour, chemicals and avoided equipment replacement. Any facility that spends time and money descaling boilers or buying anti-scaling chemicals should look at the full cost picture, not just the fuel bill.

See more results on our MHD Systems page.

Written by
Mac Trade Canada Corporation

An international trading and marketing company headquartered in Pickering, Ontario, with branch offices in Bangladesh, India, Singapore, New York and London.

Leave a comment

Your email address will not be published. Required fields are marked *

Thank you! Your comment has been submitted for review.
Please enter your name.
Please enter a valid email address.
Please write a comment.
Chat with us+1 647.213.1795